Wind farm Ponikve

The wind farm Ponikve is located on the Pelješac peninsula and it is the first wind farm developed in Dubrovnik-Neretva County. Construction of the plant began in 2011 and was put into operation in 2013. The total installed capacity of the project is 36.8 MW divided into 16 Enercon E-70 wind turbines with an individual rated power of 2.3 MW. The power plant annually produces about 65 GWh of clean electricity.

Key facts

Number of installations: 16
Type: Enercon E-70
Investment amount: 46.000.000 €
Rated power: 36.80 MW
Commissioning: 2012
Annual production: 65 GWh
Corresponds to annual consumption:    more than 70.000,00 €
Location: Dubrovnik-Neretva County